  3. How to build a padel court: from empty plot to first serve

Guide

How to build a padel court: from empty plot to first serve

Building a padel court is simpler than most people expect, as long as the steps happen in the right order. This is the order we follow on every project.

By Felix KaldalPublished 4 min read

Padel court at Lamai Padel Club built from a bare plot

Short answer

To build a padel court: check the site (about 260 m² per court, level, with access), get permission, agree a layout and quote, build the foundation (a level 15 cm reinforced slab or a raised base), let the courts be produced and shipped, then install the frame, glass, turf and lights in about 4 days per court. Plan 8–12 weeks from order to first serve, or 3–6 months with groundworks, planning or a roof.

Space≈ 260 m²per court
Foundation15 cmreinforced slab
On site≈ 4 daysper court
Order to play8–12 wkstypical

The eight steps

  1. Check the siteA doubles court is 20 × 10 m inside the walls. Plan about 260 m² per court including run-off. Check ground, drainage, access for a container truck, power and neighbours.
  2. Get permissionOutdoor courts, fencing and floodlights usually need planning approval. Start early, it is often the longest step.
  3. Agree layout and quoteChoose court model, turf, lights and options. You get a layout drawing, a fixed quote and a timeline.
  4. Build the foundationA level, reinforced 15 cm concrete slab with a gentle drainage fall, built locally to our drawings. Or a raised platform base without slab for the Prism Pano.
  5. ProductionFrames are cut, welded, galvanized and powder-coated, glass is tempered, turf is made in your colour.
  6. ShippingUp to four courts per 40-ft container, delivered to your site. You unload it.
  7. InstallationOur crew raises the frame, fits the glass, lays turf and sand and mounts the lights, in about 4 days per court.
  8. HandoverFinal checks, maintenance training, spare parts and a maintenance plan. Then first serve.

Step 1 in detail: is your site suitable?

  • Size: about 260 m² per court. See padel court dimensions.
  • Ground: firm and reasonably flat. Slopes up to 1 m can be handled with a raised base.
  • Orientation: north–south long axis outdoors, to keep low sun out of players’ eyes.
  • Access: a truck with a 40-ft container must reach the site.
  • Neighbours: padel is louder than tennis. See padel court noise.

Step 3 in detail: choose your court

We build two models. The Prism Pano has panoramic glass with slim corner pillars and is the choice for most clubs, hotels and homes. The Prism Super Pano has column-free corners and is the show court. Read panoramic vs super panoramic. Then choose turf (turf guide) and lights (lighting guide).

Step 4 in detail: the foundation

The frame bolts to the base, so the base decides how straight the court stands. Read padel court foundation for slab specifications, the UK asphalt alternative and raised bases.

Step 7 in detail: installation

Our crew installs about one court every four days on a ready slab, and works on several courts in parallel on bigger sites. The day-by-day sequence is in our installation guide.

Typical padel court project, order to first serveWeeks after signed agreement. Groundworks and production run in parallel.W0W2W4W6W8W10W12Site review and design1–2 wksPlanning permission, if neededvaries by countryGroundworks and slab (local)incl. curingProduction of courts≈ 4–5 wksSea freight and customs≈ 3–5 wksInstallation by our crew≈ 4 days/courtHandover and first serve
A typical project from order to first serve. Groundworks and production run at the same time.

What it costs

A complete Prism Pano is about US$27,660 per court in a 4-court order, delivered and installed. The slab, a roof, unloading, duties and VAT come on top. See the full price breakdown.

Price your own courtsPick model, turf, lights and number of courts. The price updates as you click.

Open the court builder

FAQ

Your questions, answered.

Still unsure? WhatsApp +46 73 509 69 60 for an answer the same day.

How long does it take to build a padel court?

About 4 days per court on site with a ready slab. From order to first serve, plan 8–12 weeks, or 3–6 months if you need groundworks, planning permission or a roof.

Can I build a padel court in my garden?

Yes, if you have about 260 m², a suitable base and permission where required. See our guide to home padel courts.

What is the first step to build a padel court?

Check the site: size, ground, access, power and neighbours. Then apply for permission and ask for a layout and quote.

Do I need a concrete slab for a padel court?

Usually yes, a level reinforced slab of about 15 cm. The Prism Pano can also stand on a raised platform base without a slab.

Who installs the court?

Prism’s own crew. Installation costs US$4,545 per court and is included in our delivered-and-installed prices.